With much intense work having gone into Project D6948 over the winter period, the onset of Spring is an ideal time to take stock of what we have done and bring everyone up to date with the state of play. What everyone wants to know of course is….when will it be finished and a pristine green and steaming D6948 emerge into the daylight and back on to its first train?
The owners have been careful not to set a specific deadline for the completion of the project, which commenced in October 2010 when 37248 was withdrawn from traffic at the GWR, given the unknowns involved. This included fitting a boiler to a locomotive that had not previously carried one and overhauling a 50 year old locomotive that has clearly had a hard life and has only recently come off the main line to name but two. ‘It will be ready when it’s ready’ has been the mantra, and no compromise will be made when it comes to ‘doing it right’. However, we are now entering what should be the final straight, and the intention is for completion to be ‘some time in the second half of 2015’, 5 years after the refurbishment project started. Continue reading →